Home sitemap english
홈 > 제품 및 기술 > 기대효과
 
2000년
PC
- 6m 7L DNS GUI Development
PLC Modify
- 9L KDNS Scheduler Development
Wet Tool Modify
- 6,7L IPA sub supply Unit Development
- 5L Bath Modify H2SO4 to SC1
- 6L Bath Modify SC1 to H2SO4
Relocation Wet Tool
- Mercury Tool Relocation (6L to 9L)
 
2001년
PC
- SES PC Upgrade Modify 6,7,8L 53Tools
PLC Modify
- 7L KDNS Scheduler Development
Wet Tool Modify
- 6,7L Digital flow control system Modify(14T)
- 6,7L Sub Sink Leak Repair Modify(10T)
- SAS L Bath Modify HNO3 to H2SO4
- 6,7L BOE Concentration Monitor Modify
- 8L Oxide Tool to Organic Strip Modify
Relocation Wet Tool
- KDNS Tool Relocation 6L to 8L
- Mercury Tool Relocation(6L to 9L)
Dryer Interface Modify
- 6,7L IPA Dryer to FST Dryer Modify(3T)
2002년
PC
- SAS SES Tool PC Upgrade Modify(12T)
PLC Modify
- SAS KDNS Scheduler Development(9T)
- 8L KDNS Scheduler Development(10T)
Wet Equipment Modify
- SAS Inline Heater Modify (H3PO4,H2SO4)
- 6,7L Sub Sink Leak Repair Modify (7T)
- 6L KDNS Tool Half Auto Modify
- 8L C/W to Rinse Modify (3T)
Dryer Interface Modify
- SAS S/D to IPA Dryer Modify
 
2003년
PLC Modify
- 7L KDNS PLC Scheduler Development(4T)
Wet Equipment Modify
- SAS HF to SC1 Modify (KAIJO Tool)
- 6L C/W to Rinse Modify
- 6,7L HQDR Leak Repair (Sub Sink 2Tools)
- SAS Digital flow control system Modify(9T)
Wet Equipment Relocation
- SAS SES Tool Relocation (3T)
- SAS SEMES Tool Relocation (1Tool)
Dryer Interface Modify
- 6L IPA Dryer to FST Dryer Modify (2T)
- 8L IPA Dryer to FCD Dryer Modify(1T)
2004년
PC
- RS L SES PC Upgrade Modify (1T)
PLC Modify
- 7L Agitation Modify (8T)
- 8L SEMES Scheduler Modify(2T)
Wet Equipment Modify
- SAS Inline Heater Modify(H3PO4)
- 6,7L HQDR Leak Repair (Sub Sink -5Tools)
- 8L C/W to Rinse Modify(2T)
- SAS BOE to SOE Modify (1T)
- 6,7L Digital flow control system Modify(4T)
- SAS SC1 /HF bath Modify (1T)
- SAS AL-E to SC1/HQDR Modify (1T)
- 7L SC1 to NSC1 Modify (1T)
Wet Equipment Relocation
- 8L SES Tool Relocation (1Tool)
Installation
- SAS 8inch Set-Up (New Pegasus)
- Samsung 12inch Set-Up (SES BW3000 12T)
 
2005년
PC
- RS L SES PC Upgrade (7T)
PLC Modify
- 8L LK201 Link Unit Modify (17T)
Wet Equipment Modify
- 6L H3PO4 DIW Digital flow control system
  Modify (2T)
- 7L Chemical sub supply unit Modify(1T)
- 9L SES Tool Circulation flow rate Modify (1T)
- 7L SC1 to NSC1 Modify (1T)
- 8L HF+OR to SC1+HQDR Modify (1T)
Wet Equipment Relocation
- 6L SES Tool Relocation (1T)
- 8L SES Tool Relocation (5T)
- SAS L Tool Relocation (3T)
Dryer Interface Modify
- 9L APET Dryer Interface Modify (1T)
Installation
- Samsung 12inch Set-Up (SES BW300010T)
2006년
PC
- 7L SES PC Upgrade Modify (5T)
- 5L SEMES Tool PC Scheduler Modify
- 10L PC Upgrade WinNT to Win2K Vb5.0 to
  Vb6.0(5Tool)
PLC Modify
- 10L SES Scheduler Modify (1T)
- 6L SEMES Stocker Robot Modify (1T)
Wet Equipment Modify
- 9L H2O2 Clean Valve Modify (45Tools
- 6L H2SO4 Circulation Modify (1Tool)
- RS L H3PO4 HF Flow Control Modify (1T)
- 6L C/W to QDR Modify (2T)
- 6L HF to SC1 Modify (1T)
- 10L M/D Hood Modify (10T)
- RS L Carrier Clean Modify (1T)
- 9L Aqua Modify (1T)
Wet Equipment Relocation
- 11L Relocation SES (3T)
- SAS L Relocation (2T)
Dryer Interface Modify
- SAS APET Dryer Interface (1T)
- 8L APET Dryer Interface Modify (1T)
- 11L PID Dryer Interface Modify (1T)
Installation
- Samsung 12inch Set-Up (SES BW3000 6T)
 
2007년
PC
- 7L SES PC Upgrade Modify
- 5,9L Scheduler PC Upgrade Modify
PLC Modify
- 8L RT1 Agitation Modify
Wet Equipment Modify
- 7L Tel Leak Repair
- SAS SES Tool Leak Repair Modify (2T)
- KAIJO Tool Leak Repair Modify (1T)
- 5L HF to NA Bath Modify
- 8,9L IPA Dryer DIW flow rate Modify (15T)
- 6L SES PC Rack System Modify (3T)
- 9L Transformer Modify (2T)
- 8L SES SC1 to NSC1 Modify (1T)
Wet Equipment Relocation
- 10L Mattson Disassembly (2T)
- Relocation 11L to 10L(2T)
- 11Line to 4Line (4T)
- Relocation 11L to SAS L(3T)
Dryer Interface Modify
- SAS L PID Dryer Interface Modify (1T)
Installation
- Samsung 12inch Set-Up (SES BW3000 6T)